Stressed vs Relaxed CPM Networks

Use Zümmer’s Total Float Distribution Curve to evaluate the condition of a CPM Network.

Overview

Analyzing and understanding the distribution of Total Float (TF) values across a CPM network is a simple but revealing health check. As a general rule, CPM networks with a more “Stressed” TF distribution are more sensitive to Project delays and claims than CPM networks with a more “Relaxed” TF distribution.

How to Read the Total Float Distribution Curve

Zümmer’s Total Float Distribution Curve report plots every task’s Total Float value allowing you to evaluate the condition of the CPM network at a glance:

  • X-axis — the Total Float value, in days.
  • Y-axis — Percentile of All Tasks: the percentage of tasks that have that Total Float value or less.

Example of a “Stressed” CPM Network

In the “Stressed” CPM Network example shown above, the 1,000 tasks span Total Float values from 0 to 200 days. Reading the curve:

  1. At the 50th percentile, Total Float is about 28 days — half of all tasks have about 28 days of Total Float or less. (Red Arrows)
  2. At the Midpoint of Total Float values (100 days Total Float) – about 82% of all tasks fall at or below the midpoint Total Float value. (Green Arrows)
  3. More than 10% of tasks have zero Total Float and sit on the Critical Path (Yellow Arrow).

Example of a “Relaxed” CPM Network

In the “Relaxed” CPM Network example shown above, the 1,000 tasks span Total Float values from 0 to 200 days. Reading the curve:

  1. At the 50th percentile, Total Float is about 108 days — half of all tasks have about 108 days of Total Float or less. (Red Arrows)
  2. At the Midpoint of Total Float values (100 days) – about 40% of all tasks fall at or below the midpoint Total Float value. (Green Arrows)
  3. Only about 5% of tasks have zero Total Float and sit on the Critical Path (Yellow Arrow).

Interpreting the Curves

All else being equal, Projects with a “stressed” distribution are more likely to have a greater potential for claims and experience delays than those with a “relaxed” distribution. A precise rule of thumb is debatable, but by observation:

  • Identifying Stressed CPM Networks — curves that are steep on the left side and flat on the right side. In Stressed CPM networks, the red arrows are well inside the green arrow boundary. Also, the percent of activities on the Critical Path is excessive. Typically, 10% or more is considered the high boundary threshold.
  • Identifying Relaxed CPM Networks — curves that rise smoothly from beginning to end. In Relaxed CPM networks, the green arrows are typically inside the red arrow boundary. Also, the percent of activities on the Critical Path is low. Typically, 5% or below is considered the low boundary threshold.

When to Take Action

A closer look at the schedule’s logic may be warranted when either Stressed or Relaxed conditions exists in the extreme.

  • Very stressed distributions may signal a “claims-oriented” schedule. Review the overall logic to find relationships that can be removed or revised, thereby increasing overall Total Float.
  • Very relaxed distributions may signal an insufficiently developed schedule. Review the overall logic to find relationships that can be added or revised, thereby decreasing overall Total Float.

Copyright ©2026 FoxQuest Systems, Inc. – All Rights Reserved

New Release of CPM Schedule Analysis & Comparison with Zümmer and Manual 12th Edition

Find out what’s new and improved in Zümmer.

Zümmer has been a proven and successful tool for analyzing and comparing CPM schedule for over 14 years now.

Since its official release in 2012, Zümmer has never set still. Improvements to the applications features and reporting tools have been a continuing effort. Thanks in part to many suggestions received over the year by its faithful and enthusiastic users. It is our goal to continue to improve on its features and functionality as long as CPM schedule continues to be the industry standard in construction scheduling.

We understand that deciding on a suitable CPM analysis & comparison tool can be a complicated decision for any organization and especially for larger organizations with extensive IT rules and guidelines. Therefore, our team is dedicated to making your decision as streamline as possible.

Zümmer has been tested and evaluated by some of the largest organizations in the construction industry and has passed Risk Assessment evaluation tools such as Crowdstrike Threat assessment testing with flying colors.

In addition, to make your decision-making process easier, you can download the entire Zümmer Manual here for free! (601 Pages, 46MB).

Some new Zümmer features include:

  1. Improved Activity Finish History graphing:
  • Activity Status indicators on the Finish Date line graph.
  • Data Date line graph with data point value that indicates #Days to Finish.
  • Green shading between Data Date line & Finish Date line added for easier viewing.
  • Improved Activity Finish History Report.

2. Improved Activity Finish History Trending

  • Activity Status indicators on the Finish Date line graph.
  • Data Date line graph with data point value that indicates #Days to Finish.
  • Green shading between Data Date line & Finish Date line enhances forensic analysis.
  • Easier to read trendline.
  • Improved Activity Finish Trending Report.
  • Automatically outputs to Excel Spreadsheet.

3. Added Activity Logic History Module:

  • Track, print & analyze logic changes to any selected activity across multiple Project Updates.

4. Added Activity Cost History Module – Graphing:

  • Graphically plot Activity Resource Cost status across multiple Project Updates.
  • Preview & Print Tabular Activity Cost Report across multiple Project Updates.
  • Automatically outputs Activity Graph to Excel spreadsheet.

5. Added Activity Cost History Module – Trending:

  • Plot Activity Cost Trending “Burn Rate”.
  • Automatically outputs Cost Trend to Excel spreadsheet.

6. Added Project Cost History Module – Graphing:

  • Graphically plot Project Resource Cost status across multiple Project Updates.
  • Preview & Print Tabular Project Cost Report across multiple Project Updates.
  • Automatically output Project Cost Graph to Excel spreadsheet.

7. Added Project Cost History Module – Trending:

  • Plot Project Cost Trending “Burn Rate”.
  • Automatically output Project Cost Trend to Excel Spreadsheet.

8. Added Activity Expense History Module – Graphing:

  • Graphically plot Activity Expense status across multiple Project Updates.
  • Preview & Print Tabular Activity Expense Report across multiple Project Updates.
  • Automatically outputs Activity Expense Graph to Excel Spreadsheet.

9. Added Activity Expense History Module – Trending:

  • Plot Activity Expense Trending “Burn Rate”.
  • Automatically outputs Activity Expense Trend to Excel Spreadsheet.

10. Added Project Expense History Module – Graphing:

  • Graphically plot Project Expense status across multiple Project Updates.
  • Preview & Print Tabular Project Expense Report across multiple Project Updates.
  • Automatically outputs Project Expense Graph to Excel Spreadsheet.

11. Added Project Expense History Module – Trending:

  • Plot Project Expense Trending “Burn Rate”.
  • Automatically outputs Expense Project Trend to Excel spreadsheet.

In addition, you can download a free 30-Trial of Zümmer for MS-SQL and SQLite here.

©2026 FoxQuest Systems, Inc. All Rights Reserved