How To: Perform a CPM Schedule Comparison

Comparing P6 CPM schedules in Zümmer is easy and intuitive!

 
Step 1:


From the Schedule Analysis & Comparison Module (See Illustration above), select the first Project ID in the Control grid, then select the second Project ID in the Modified grid. As you select, the tab descriptions to the right of the “Project Selection” adjust accordingly.

Step 2:

Click on the rightmost Tab. Then move the reports from Available Reports list to the Select Reports list.

In the illustration above, Comparison Reports 1 thru 20 are selected are ready for printing or previewing.

Check the “Include Summary” checkbox to print a Summary Comparison Report after all selected reports are printed. Lastly, click either Print or Preview and you’re done.